PROGRESS OF THE DRALOD PILOT PLANT IMPLEMENTATION
In June, we have started to recover some normality in our daily businesses. The implementation works have restarted in Chiloeches, under the leadership of L.PERNIA SA. The installation of the SolarWall roof is now finalised. The preparatory works for the installation of the biomass heating system have started. The foundation for a biomass feeding system with moving floor, is now built. The drum dryer has been transported to the plant and its installation works have now started. Thus, the installation of the main subsystems of the DRALOD pilot plant is on-going and progressing according to plan. The installation completion date is foreseen in September 2020.


DRALOD is co-funded by the European Commision - Horizon 2020 Programme - under Grant Agreement 820554